Remediation Project – March 2022
Over a 10-day period, Gregg Remediation injected approx. 62,000 total gallons into 12 direct push locations, targeting 3ft treatment zones from 38-65ft bgs. Injected amendments included a 2% EVO solution with sodium bicarb, anoxic/chase water, and DHC.
Highlights:
- Chemical mixing truck had to be demobilized daily due to site logistics
- Inline mixing of the EVO allowed for increased mixing precision compared to batch mixing
- Injected at six (6) simultaneous injection locations